On April 28, 2003 at 1:00pm, we had our ninth project meeting with Michele. Dana, Dave, and Jason were all present.
Notes by Dana Champion
Definition of "Done":
Michele gave us the thumbs-up this definition of done. Michele would like us to record which requirements have been implemented and which have not, for future reference. We will do this as part of our document of application functionality.
We will meet with Gender Initiative the morning of Tues May 6 to wrap-up with:
At this meeting, we presented Michele with a prototype that had all levels of functionality implemented "roughly" and just needed some prettying-up and bug fixes. We split up the test plan between the four of us and spent some time testing & recording results. Remaining Tasks / Test Results:
| Page Execution took real: 1.841, user: 1.430, sys: 0.080 seconds |