Milestone Completion Summary for CSC333 (Spring, 2003)

Milestone Number: 5

Team Name: Gender Initiative Project

Team Members (and Roles, including leader):

Due Date: 22 Apr 2003

Summarize Results of Milestone:

Strengths of Milestone:

Weaknesses of Milestone:

Project Status:

Effort:

Dana Champion Meetings / Presentation 3 hours
Calendar View/Approve/Reject Event Request Implementation 6 hours
M5 Implementation Status < 1 hour
M6 Intentions Document < 1 hour
Update Project Plan < 1 hour
Meeting notes < 1 hour
Completion Summary 1 hour
Dave Lanzer Meetings 1 hour
Contacts / Library Implementation 10 hours
Performance Improvements 1 hour
Jason Long Meetings 1 hour
Status Reports 1 hour
Library DFD 1 hour
View Event Requests Implementation 2 hours
Test Plan 8 hours